Cogen facility at Thurso passes test to provide green power

Pulp & Paper Canada
April 07, 2015
By Pulp & Paper Canada

Fortress Paper Ltd. has successfully completed the mandatory 100-hour test for its cogeneration facility at the Fortress Specialty Cellulose Mill in Thurso, Que. This will allow for the addition of 5.2 MW of incremental power. The cogeneration facility can now deliver up to 24 MW of power to Hydro Québec at the contract commercial rate.

The successful test follows completion of certain gear repairs to the cogeneration facility. After the repairs, the ramp-up of the cogeneration facility proceeded smoothly, the company states.

Chadwick Wasilenkoff, CEO of Fortress Paper, thanked the team at the FSC mill for their efforts in promptly repairing the cogeneration facility and ramping-up power production. He described to delivery of 24 MW of power as “an important step in our plans to continue lowering production costs at the FSC Mill."

The Fortress Specialty Cellulose mill can produce dissolving pulp or northern bleached hardwood kraft pulp, as well as green power.

Add comment

Disclaimer
Note: By submitting your comments you acknowledge that Pulp and Paper Canada has the right to reproduce, broadcast and publicize those comments or any part thereof in any manner whatsoever. Please note that due to the volume of e-mails we receive, not all comments will be published and those that are published will not be edited. However, all will be carefully read, considered and appreciated.


Security code
Refresh

Subscription Centre

 
New Subscription
 
Already a Subscriber
 
Customer Service
 
View Digital Magazine Renew

Most Popular

Latest Events

TissueCon 2019
October 1-4, 2019
BLRBAC Fall 2019 Meeting
October 14-16, 2019
TAPPI PEERS 2019
October 27-30, 2019

We are using cookies to give you the best experience on our website. By continuing to use the site, you agree to the use of cookies. To find out more, read our Privacy Policy.